Section 10 Wastewater Plant Expansion Concerns
Summary
Nearly $5.8 million approved for two blower buildings at the Section 10 plant and new membranes at Section 18 — invisible but essential spending paid through sewer rates near the Colorado River watershed.
At a glance
- Total mentions
- 11
- Last 30 days
- 3
Rising — discussed at 5 meetings since Oct 6, 2026, up from 2 in the two months before.
Impact analysis
Funded by sewer customer rates through the enterprise fund, not general taxes.
All sewer customers who rely on the two regional treatment plants near the Colorado River.
Ratepayers facing prior utility rate adjustments implemented to fund capital improvement projects.
Mentions & discussions (11)
Regular City Council Meeting AMENDED - Nov 3, 2026
The 18-2 Lift Station lost a major pump to an electrical failure, and the council approved a $76,490 rebuild rather than a new pump. A frequent commenter pressed for a full inventory of aging pumps and backup equipment citywide.
Parks & Recreation Commission Meeting - Oct 21, 2026
Residents expressed concerns about unmanaged standing water and drainage issues creating mosquito problems in neighborhoods.
Board of Adjustment (Regular) - Oct 13, 2026
The city council approved nearly $5.8 million in contracts for wastewater treatment plant upgrades, including blower building improvements at Section 10 and membrane replacements at Section 18. These investments ensure compliance and system reliability, funded through utility enterprise funds and user fees.
Planning and Zoning Commission Meeting - Oct 8, 2026
The city approved nearly $5 million for blower building improvements at the Section 10 wastewater plant and over $800,000 for membrane replacements at the Section 18 plant to protect the Colorado River and maintain infrastructure.
City Council (Regular) - Oct 6, 2026
Nearly $5.8 million approved for two blower buildings at the Section 10 plant and new membranes at Section 18 — invisible but essential spending paid through sewer rates near the Colorado River watershed.
Special City Council Meeting - Executive Session - Aug 17, 2026
Utilities staff updated the public on the Section 10 Wastewater Treatment Plant expansion, assuring residents that construction staging is entirely on city property and does not disturb the nature center.
City Council (Regular) - Aug 17, 2026
Utilities officials addressed resident complaints about ground disturbance near the Section 10 Wastewater Plant, explaining that the clearing is entirely on city-owned land reserved for expanding plant capacity and does not affect the nearby Nature Center.
Special City Council Meeting - Executive Session - Aug 4, 2026
The city approved a $1.56 million contract to install 4,700 feet of 16-inch water transmission main along North Oatman Road, completing the final phase of the South Supply Line project to improve water pressure and capacity in southern Bullhead City.
City Council (Regular) - May 5, 2026
The city approved engineering contracts to expand the Section 10 plant capacity from 4 million to 6 million gallons per day, adding a solids dewatering system and UV disinfection trains to lower operating and sludge-hauling costs.
City Council (Regular) - Mar 3, 2026
The city is moving forward with a massive $11.1 million upgrade to expand wastewater treatment capacity and replace aging equipment. Residents asked questions about potential rate impacts and equipment durability during the public hearing.
Bullhead City Launches Comprehensive Maintenance And Infrastructure Improvement Projects Week Of March 2
Bullhead City Launches Comprehensive Maintenance And Infrastructure Improvement Projects Week Of March 2 thebee.news
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bullhead City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.