Ramsey Canyon Shared Use Path Grant Rejection
Summary
Public Works and engineering staff updated the Board on the ADOT-funded shared-use path along Ramsey Canyon Road, noting high construction costs, utility pole relocations, and federal grant restrictions.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 11, 2026.
Impact analysis
Requires local match funding of approximately $133,000 against a total project cost exceeding $2.3 million.
Pedestrians, cyclists, and recreational trail users seeking separated pathway infrastructure.
County road maintenance programs facing potential opportunity costs and diverted resources.
Mentions & discussions (2)
Regular Board of Supervisors Meeting — August 11, 2026
Supervisors deadlocked on a $2.3 million ADOT grant to extend the Newman Trail, turning down federal funds because of concerns that the path would terminate near State Route 92 without adequate highway safety separation for cyclists.
Work Session Board of Supervisors (Work) — August 6, 2026
Public Works and engineering staff updated the Board on the ADOT-funded shared-use path along Ramsey Canyon Road, noting high construction costs, utility pole relocations, and federal grant restrictions.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Cochise County, Arizona
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.