Wastewater Treatment Plant Centrifuge Replacement
Summary
The council approved a $1.2 million contract to replace a failing centrifuge at the wastewater treatment plant to maintain regulatory compliance and reduce sludge hauling costs.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 7, 2026.
Impact analysis
The project costs $1,217,409, supported by an $18,000 project budget increase and internal fund reprioritization.
Public Works operations and the city benefit from improved operational efficiency, lower electrical consumption, and reduced sludge hauling costs.