Southern DFW RPG project

Summary not yet generated for this topic.

Community sentiment

Supportive (2)

At a glance

Public comments
2
Last 30 days
0

Last discussed Mar 25, 2026.

Public comments (3)

SupportiveBrett CollardMar 25, 2026

Compass Data Centers has an energized 667 MW campus in the region and offered financial participation in transmission through its co-serve model, saying it does not want to strand residential ratepayers.

Technical Advisory Committee - Mar 25, 2026 · 2:13:36 →
SupportiveJustin LaufMar 25, 2026

Providence Data Centers described its Grand Prairie project — an executed 500 MW interconnection agreement, $100 million committed, active construction — as proof the load is real, urging prompt endorsement.

Technical Advisory Committee - Mar 25, 2026 · 2:15:09 →
SupportiveChris MatosMar 25, 2026

Google's representative said its two south Dallas data centers were delayed by the process, stressed minimum transmission charges to protect ratepayers, and asked about the gap between batch zero and batch one.

Technical Advisory Committee - Mar 25, 2026 · 2:20:51 →