A project reclassified from Tier 2 to Tier 1 to serve over 1,100 MW of attested green ammonia load in Noesis County; TAC endorsed ERCOT's recommended $161 million Option 3.
Impact summary
Adds network in an area that has historically lacked it, supporting a second large ammonia plant load in the region.
Applicant
- Name
- Steck
At a glance
- Hearings
- 1
- Public comments
- 0
- Total mentions
- 1
Last vote
A recommendation. The council’s outcome is not on record here.
Last discussed Mar 25, 2026.