Marana Main Street Development Agreement amendment
Summary
The Town agreed to pay the Main Street developer $300,000 for building Main Street and Center Street, plus $19,265.89 in shared water/irrigation costs. The roads were originally due by June 2021 but were substantially completed in July 2024 — this amendment formalizes the reimbursement based on that later date.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
$319,265.89 from the Downtown Marana Reinvestment Fund and town water/irrigation cost sharing.
The developer receives the promised reimbursement; downtown Marana gains completed streets and an updated plan for remaining parcels.