Pavement condition and street maintenance funding
Summary
Five road projects are being prioritized for street bond funding: Glassford Hill Road safety turns, Florentine Road widening, Viewpoint Drive improvements, north-side east-west connectivity, and the Lakeshore/Navajo intersection.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 1, 2026.
Impact analysis
Roughly $9 million identified for the top two projects, funded primarily by a continuation of the town's street bond.
Drivers, pedestrians, and cyclists across town, especially on Florentine and Glassford Hill corridors.
Mentions & discussions (2)
Town Council Study Session — October 1, 2026
The town's 4.4 million square yards of pavement is worth roughly half a billion dollars and currently scores 75 out of 100. Holding that score needs about $5 million a year, but the budget is $3.5 million, so road conditions would slowly decline over five years.
[Archived] Town Council Study Session - Thursday — April 2, 2026
Five road projects are being prioritized for street bond funding: Glassford Hill Road safety turns, Florentine Road widening, Viewpoint Drive improvements, north-side east-west connectivity, and the Lakeshore/Navajo intersection.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Prescott Valley
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.