US 95 water and sewer main design
Summary
The council hired Core Engineering for $93,558 to design about 1.5 miles of water and sewer mains along US 95 — the next step in a $1.2 million federal grant project with local match, supporting growth along the highway corridor.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 12, 2026.
Impact analysis
$93,558 for design, within a roughly $1.7 million project backed by a $1.2 million federal grant.
Residents and businesses along the US 95 corridor needing utility capacity.