Project Bacara Power Plant and Data Center Proposal

Summary

Commissioners requested a future staff review of city rules governing data centers to prepare for potential high-tech employment developments in Surprise.

At a glance

Total mentions
6
Last 30 days
0

Last discussed Apr 7, 2026.

Impact analysis

💰Financial impact

Potential future economic development and tax base enhancement.

✅Who benefits

The local economy and residents seeking high-tech employment opportunities.

⚠️Who could be affected

Residents living near the proposed facility facing potential emissions and noise impacts.

Mentions & discussions (7)

MeetingApr 7, 2026

Regular City Council Meeting - Apr 7, 2026

Residents urged the city to formally oppose the Project Bacara power plant and data center proposed within Luke Air Force Base accident potential zones.

MeetingJan 20, 2026

Regular City Council Meeting - Jan 20, 2026

Residents voiced strong opposition to the proposed Project Picara data center and gas turbine power plant project near Surprise, citing air pollution, water consumption, and health risks.

MeetingDec 16, 2025

Regular City Council Meeting - Dec 16, 2025

Residents spoke out against the massive proposed industrial Project Bacara, citing severe concerns over water usage, health impacts, proximity to residential areas, and emergency services.

MeetingSep 16, 2025

Regular City Council Work Session - Sep 16, 2025

Residents near the proposed Bacarra data center project just outside city limits are worried about constant noise from 18 large generators, water usage, and air quality. Although the project is in Maricopa County, Surprise city leaders are pushing for thorough impact studies and emergency plans since local police and fire will be first responders.

MeetingSep 2, 2025

Regular City Council Meeting - Sep 2, 2025

Residents and county neighbors expressed strong opposition to Project Bacara, a proposed 700-megawatt natural gas power plant and data center near Waddell, citing severe concerns over groundwater depletion, air pollution, noise, and home equity loss.

MeetingJul 17, 2025

Planning and Zoning Commission - Jul 17, 2025

Commissioners requested a future staff review of city rules governing data centers to prepare for potential high-tech employment developments in Surprise.

Surprise Independent (Your Valley)

Split Glendale Planning Commission recommends rezoning for data centers, power plant - Surprise Independent

By a 4-2 vote Sept. 24, the Glendale Planning Commission recommended a rezoning of the Project Eagle data center and Project Baccara natural gas power plant. The City Council will vote on the …

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Surprise

Every council decision, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.