La Quinta retention basin upgrades
Summary
The council looked at a $406,615 contract with Accurate Excavation of Arizona to upgrade a city-owned stormwater basin, including a lift station that will pump stormwater onto nearby school fields.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
$406,615 for construction, noticeably cheaper than the other bids received.
La Quinta neighborhood residents who rely on the basin for stormwater drainage.
Mentions & discussions (1)